Construction of gabion basket weir with trash rack in a natural waterway.
| Client | Contract Value | Duration |
|---|---|---|
| DPTI - Department of Planning, Transport and Infrastructure | $170,000 | 3 weeks |
Construction of gabion basket weir with trash rack in a natural waterway.
DPTI engaged Davison Earthmovers to undertake work involving:
In order to achieve the required outcome an innovative method for establishment into the site was required involving:
Use of rubber tyred excavator for access through rail corridor and placement of rock and other materials onto slipway