Client Contract Value Duration
BesixWatpac $12 million In progress.....commenced October 2023

Description

Davison Earthmovers have been contracted to complete the bulk earthworks and civil & stormwater works for the new SAPOL Mounted Operations Unit. Site location on the corner of Grand Junction & Briens Road, Northfield.

April 2024

Scope of Works

  • Total site area 80,000m2.
  • Site strip and vegetation processing (based on 27,000m3).
  • Cut to fill bulk earthworks with Level 1 geotechnical control for building pad works and roadways (25,000m3 site won fill and 30,000 ton of imported fill).
  • Building pad preparation and final trimming.
  • Civil pavement construction for heavy duty/light duty concrete pavement.
  • Detention basin with Elcoseal liner and associated stormwater.
  • Stormwater pit and pipe installation.
  • Construction of concrete sleeper retaining walls.
  • DIT roadworks of new slip lane entry (Grand Junction Road).