Sam Willoughby BMX Facility, Southern Soccer Facility & Majors Road Upgrade

Client:

Partek Constructions

Contract value:

$3 million (incl GST)

Description:

Earthworks and Civil Package for the new Sam Willoughby BMX Facility, new Southern Soccer Facility and Majors Road Intersection upgrade.

Duration:

Commenced March 2021..... in progress

Scope of works:

  • 67000m3 of cut to stockpile for spectator viewing mounds construction, including shaping and final trim of the mounds.
  • 12,000m2 of carpark construction and spray seal surfacing.
  • 3,500m3 of building pad fill remediation under level 1 control.
  • Swale construction and detention basin earthworks and final trimming.
  • 2km of concrete kerbing and 1,100m2 of footpath construction.
  • Preparation of 3 full sized soccer fields and warm up area.
  • New pavements, deep lift asphalt, lighting and signal upgrade works for DIT Majors Road for the new BMX facility entrance.

Southern Soccer Facility - October 2021

Southern Soccer Facility - November 2021

Sam Willoughby BMX Facility - October 2021

Sam Willoughby BMX Facility - November 2021

Majors Road & Adams Road, O'Halloran Hill upgrade - November 2021

Commencement

Commencement